Finns Rd / Remembrance Driveway Roundabout

Background

Council has successfully secured funding through the State Government Road Safety Package – Black Spot Program to upgrade the Finns Rd and Remembrance Driveway intersection to a two lane roundabout.

The introduction of the roundabout aim to address the poor crash record of the intersection and improve vehicle level of service for growing traffic volume.

 

Map of proposed works

 

Details

The upgrade will introduce a large diameter two lane roundabout with street lighting, non-skid road surface, kerb and gutter, widened shoulders and traffic calming features (new road alignments/levels, splitter islands, line marking and signage).

 

Timeframe

Activity

Status

Timeframe

Project Conception

Complete

12 weeks

Field Investigations

Complete

4 weeks

Design Procurement

Complete

4 weeks

Design

Underway

16 weeks

Construction Procurement

Up coming

4 weeks

Construction

Not commenced

16 weeks

Project Completion

Not reached

Milestone

 

Impacts during Construction

More information will be posted as the Construction Phase nears.