Silverdale Road Safety Upgrades

Background

Council has successfully secured funding from both the NSW Road Safety Program – Safer Local Government Roads and Western Sydney Infrastructure Plan – Local Roads Package to implement road safety upgrades along Silverdale Road. Collectively these grants will provide $10 million over three years to enable Council to upgrade road segments which have had poor crash history and improve the road utility through Silverdale township.

 

Details

Silverdale Rd from The Oaks to Silverdale (Stage 1) will receive targeted upgrades which aim to improve the crash history of the road. Upgrades will include features such as non-skid road surface, safety barriers, street signage and reflectors, improved line marking and sealed road shoulders.

Silverdale Rd through Silverdale township (Stage 2) will receive a consistent urban two lane road profile including sealed shoulders, kerb and gutter, shared pathway and traffic calming features.

Location

Silverdale road safety upgrades map2

Before

Silverdale road before safety upgrade2

Indicative After

Silverdale road indicative after works2

 

Timeframe

Activity

Status

Timeframe

Project Conception

Complete

16 weeks

Stage 1 Field Investigations

Not commenced

4 weeks

Stage 1 Design

Not commenced

26 weeks

Stage 1 Construction

Not commenced

2021 - 2023

Stage 2 Field Investigations

Underway

4 weeks

Stage 2 Design

Underway

26 weeks

Stage 2 Construction

Not commenced

2021 - 2022

Project Completion

Not Reached

Milestone

 

Impacts during Construction

More information will be posted as the Construction Phase nears.