Blaxland Bridge Repairs - Modifications to Works Schedule

Warragamba Panorama

Blaxland Bridge Repairs - Modifications to Works Schedule

Posted on: 24.03.2017

Wollondilly Shire Council wishes to advise that the award of the contract for the Blaxland Crossing Bridge Bearing Replacement project is now scheduled for late April 2017. Due to unforeseen circumstances Council has had to delay issuing a contract to a tenderer.

Council is currently clarifying a critical technical component of the project based on the submitted tenders and, once clarified, Council can award the contract to a tenderer. Please be assured that Council are working towards a better outcome for those that use the road and for those that live and work near the area. We are reviewing the tenders so that we can choose a tender that can potentially reduce the amount of road closures needed and ultimately cause fewer disruptions during the repair works.

Michael Malone, Director Infrastructure & Environment said,
“Undertaking additional technical assessments are a necessary part of completing an appropriate tender process for a complex project and it will minimise the chances of significant issues during the bearing replacement works.

The delay in considering the tenders will unfortunately also delay the start of the fabrication process for the replacement bearings as this cannot start until the tender is accepted

We now expect the on-site works to be completed by September, with the removal of all traffic management systems and testing by October 2017.”

If you do have concerns and would like to discuss the project with Council you can contact Council’s Infrastructure Projects Officer on P: 4677 1100. Or further information on the project please see council’s website at: