Broughton Pass - Wilton Road

Broughton Pass 2

Broughton Pass is Open signage

Wilton Road at Broughton Pass is now open. It was closed due to the retaining wall failure that occurred during the storm event on 5 June 2016.

The retaining wall, located on the Wilton side of the bridge over the Cataract River, is approximately 6 metres high and was constructed in the late 1800’s of dry stacked sandstone blocks. The wall failed sometime on the afternoon of Sunday 5 June 2016, taking a section of road with it. Without the retaining wall the road is unsupported and therefore not safe for opening to traffic.

Council is treating this as a high priority matter and investigation works are completed and a tender for the design and reconstruction contract has been awarded and the works are under way.

We also engaged NSW Public Works to manage the reconstruction project. Council is seeking funding assistance through the Federal and State Government Natural Disaster Relief and Recovery Arrangements to assist with the costs of repairs.

The road will was closed until 30 June 2017 – as the extent of the works are significant, however it is now open.

Click here for more facts and images of Broughton Pass

 Broughton Pass Draft Schedule of Works

This schedule provides an indication of the likely timeframes for the re-opening of Broughton Pass and is subject to change as the project circumstances become clearer  or alter as the design and construction phases continue and required final agency approvals are obtained for the completed design.

Click on the stage for more information 

Stage

Timeframe

Status

Initial Investigation

July to early August

Complete

Concept Design Development & Review

August to January

Complete

Preliminary Expression of Interest Process

mid-August to October

Complete

Design & Construct Tendering Process

October to end of November

Complete

Procurement decision & engaging a contractor

December

Complete

Detail Design Phase by Contractor

Early March

Complete

Engagement with Community
on Design & Works Program

Early March

Complete

 Construction Phase

Early March to July 2017

Underway

 Opening of Road

 By July 2017

 COMPLETED