Works are progressing slowly due to weather conditions. The good news is, we have roughed in the plumbing and slab preparations are in progress for formwork. The new entry road is taking shape and lift pit has been installed.
Excavation works have now begun on the new building.
We have now received our long awaited LvL beams, so work has recommenced on the amenities building located near the BMX track.
The construction of a new two storey multi-purpose amenities building at Tahmoor Sporting Complex is set to commence this month, thanks to funding through the NSW Government Resources for Regions, the Western Parkland City Liveability Program as part of the Western Sydney City Deal, the Greater City Sport Facility Fund and Council contributions.
Project Coordination have been awarded the tender for construction, with the works scheduled to take 9 months. The project is anticipated to be completed by October 2022.
We’re continuing to work on delivering modern and user-friendly facilities at Tahmoor Sporting Complex. The impacts of the pandemic are evident with the building industry seeing a supply shortage which has affected the completion of the amenities building, located near the BMX track.
Rest assured, we are working closely with our building contractor GWP Constructions to ensure we are able to deliver a brand new toilet facility for the community as soon as possible. To date, block works including the slab and plumbing works have been completed.
Progress updates:
Progress updates:
Athletics:
Netball:
Cricket:
The following works have been achieved:
The following works have been achieved:
Take a look at the Tahmoor Sporting Complex works progress!